PRESS RELEASE: Line Not Needed to Supply Propane to Michigan

FOR IMMEDIATE RELEASE: February 26, 2018
CONTACT: Sean McBrearty, Oil & Water Don’t Mix, (616) 516-7758

Line 5 Not Needed to Supply Propane to Michigan
Snyder and Schuette Putting U.P. Residents and Great Lakes at Risk by Not Pursuing Alternatives
LANSING- Citizens groups gathered at the Michigan Pipeline Safety Advisory Board meeting today to call attention to new information regarding the Upper Peninsula’s propane supply from Enbridge Energy’s Line 5 pipeline. Both state authorities and Enbridge Energy representatives claim that decommissioning Enbridge’s antiquated and corroding Line 5 pipeline would significantly impact the propane supply in the Upper Peninsula. This claim is not accurate according to a recent study by retired Dow Chemical Facilities Engineer Gary Street released by Oil & Water Don't Mix.

“Enbridge currently claims that 65% of the propane in the Upper Peninsula is supplied by Line 5. In the recent past, they claimed as much as 85%. Data from the U.S. Census Bureau does not support either of these claims; the actual amount of propane supplied to customers in the Upper Peninsula that originates with Line 5 is about 45-50%. Nevertheless, whether it is 85%, 65% or 45%, the customers in the Upper Peninsula who rely on propane must be assured of an uninterrupted supply,” said Street.

“It is important to note that Line 5 will be shut down at some point in the near future. Whether that is by government edict or rupture remains to be seen. Either way, the fact remains that state authorities owe it to the Upper Peninsula propane customers to have a backup plan in place to ensure uninterrupted propane supply in the event that Line 5 is shut down,” said Bill Latka, co-founder of TC350, noting that Line 5 has previously ruptured at least 29 times in its history. “Instead of planning to ensure that the Upper Peninsula’s propane needs are met in the short term as we transition towards more renewable sources of energy, Governor Snyder and Attorney General Schuette have used the propane issue as an excuse to keep this old and dangerous pipeline operating for as long as possible.”

According to Street’s research, several prudent alternatives exist that could provide the amount of propane needed to U.P. customers in the event of a Line 5 shut down, including the following:
  • Installing a 4-inch propane pipeline from Superior, Wisconsin, to Rapid River, Michigan, along the current route of Line 5. A study prepared for MPSAB confirmed this conclusion.
  • Connecting the Plains All American Rapid River propane processing plant to a nearby rail line and moving propane from Superior, Wisconsin, by rail. Just 1-2 rail propane rail cars per day would be required.
  • Using 3-4 tank trucks per day to transport propane from Superior, Wisconsin, to the Plains All American Rapid River propane processing plant

Line 5 propane from the Rapid River plant is currently transported by truck from the plant to where the propane is needed in the Upper Peninsula, so that part of the delivery would not have to change at all.

“All that we are lacking now is leadership, and the political will to protect our Great Lakes by decommissioning this pipeline. So far Governor Snyder and Attorney General Schuette have acted as if they are beholden to Enbridge instead of the voters who elected them and trusted them to protect our water resources,” said Oil and Water Don’t Mix Campaign Coordinator Sean McBrearty. “Tens of thousands of Michigan residents from Detroit to Copper Harbor have been calling on our Governor and Attorney General to exercise their legal authority as public trustees to decommission this pipeline and prioritize our public waters. It is time for them to stop presenting misleading information about propane and start the process of protecting our water by decommissioning Line 5 immediately, before it ruptures. If they were really concerned about the U.P.’s propane supply, there would be a plan already in place in case Line 5 does rupture. The time for action is now.”

Oil & Water Don’t Mix recently released a Line 5 Decommission Plan, which can be found in full at www.oilandwaterdontmix.org/a_clear_plan_to_decommission_line_5 

###

Oil & Water Don’t Mix is a broad campaign of organizations, citizens and businesses across Michigan who are working to keep oil out of our Great Lakes by shutting down the dangerous, 64-year-old Line 5 Pipelines in the Straits of Mackinac. The campaign fights for clean water and air, Indigenous rights, reducing pollution, sustainable economies and protecting sporting, tourism and jobs that are dependent on our water and Pure Michigan way of life.